May - June 2025
Executive Summary
Governance Proposal Reviews
Total proposals reviewed: 31
Proposals approved: 30
Proposals rejected/modified: 1
Issues requiring proposal cancellation: 1
Proposals required actions other than cancellation: 5
Code Reviews Completed
Projects reviewed: 4
-
Pool V3.5 - Review in progress.
- An upgrade aiming to improve the mathematical precision of operations in the protocol.
-
Pool V3.4 - Re-audit - The review is finished. The report will be released soon along with the code.
- A collection of security and UX upgrades to Aave core. A great elaborated post on the upgrade can be found in BGDβs thread.
-
Pool V3.4 Activation AIP - The review is finished. The report will be released soon along with the code.
- A set of contracts to be executed by the governance, applying the pool logic upgrade from V3.3 to V3.4, setting and syncing the components (e.g. gho) to have a smooth transition as per the planned upgrade.
-
Swap Steward - The review is finished. The report will be released soon along with the code.
- A steward that facilitates token swaps via CoW Swap in a generalized manner that eliminates the manual contract/tx building for each swap.